400 Echo Hill Rd., Marion
Opened Fall
2008
Principal: Mr.
Dan Ludwig |
|
For attendance boundaries click here |
|
 |
|
August 2008
School is in session and students are enjoying all the building
has to offer. |
|
 |
|
1/21/08
Cabinetry is being installed in some classrooms. |
|
 |
|
1/21/08
Interior painting is underway. |
|
 |
|
November 2007
The limestone facade of Echo Hill is complete. |
|
 |
|
9/26/07
The front of Echo Hill faces northeast. |
|
 |
|
8/7/07 The
masonry at Echo Hill progresses. |
|
 |
|
6/15/07
Groundbreaking ceremony. |
|
 |
|
10/13/06 Dump
trucks bring fill dirt onto the construction site. |
|
 |
|
10/2/06
Site preparation has begun. |